Wika, the main contractor for the Kijing Port Construction Project, hired us to speed up piling works which was behind schedule in January 2020. Our highly skilled team equipped with our own SWI Sulawesi X piling barge were soon deployed to the project site. Our mission was to safely and precisely drive as many piles as possible for two months. The piles were concrete pipe, 1-m diameter and typically longer than 60 meters. Within two months, we were able to drive almost 200 piles, a significant savings in time and money for our client.
Besides accomplishing the mission, we were able to uphold our high standard in housekeeping and working condition at sea which were of great importance to the project and its workers.